What to Expect: The Concrete Pool Construction Process

Knowing what to expect removes the stress. Here’s what happens step by step.

Stage 1: Design Consultation (Week 1)

Site visit, measurements, design discussion. A detailed written proposal after the site visit.

Stage 2: Approvals (Weeks 2-4)

DA preparation, engineering drawings, council lodgement. 2-4 weeks typical.

Stage 3: Excavation (1-2 days)

The dramatic stage — your hole appears in a day or two.

Stage 4: Steel and Plumbing (3-5 days)

Reinforcement bars, plumbing, electrical conduits. Council inspection of steelwork.

Stage 5: Concrete (1-2 days)

Shotcrete applied to the steel framework. Hand-finished and profiled.

Stage 6: Curing (7-14 days)

Essential quiet period. The shell is kept damp for proper curing.

Stage 7: Tiling and Coping (3-5 days)

Waterline tiles, coping stones, feature tiles.

Stage 8: Interior Finish (2-3 days)

Pebblecrete, glass-bead, or full tiling applied.

Stage 9: Equipment and Fencing (3-5 days)

Pump, filter, chlorinator, heater, lights, automation, fence.

Stage 10: Fill and Handover (1-2 days)

Pool filled, equipment commissioned, water balanced, handover walkthrough.

Total Timeline

Design + approvals: 3-6 weeks. Construction: 6-10 weeks. Total: 9-16 weeks.