Knowing what to expect removes the stress. Here’s what happens step by step.
Stage 1: Design Consultation (Week 1)
Site visit, measurements, design discussion. A detailed written proposal after the site visit.
Stage 2: Approvals (Weeks 2-4)
DA preparation, engineering drawings, council lodgement. 2-4 weeks typical.
Stage 3: Excavation (1-2 days)
The dramatic stage — your hole appears in a day or two.
Stage 4: Steel and Plumbing (3-5 days)
Reinforcement bars, plumbing, electrical conduits. Council inspection of steelwork.
Stage 5: Concrete (1-2 days)
Shotcrete applied to the steel framework. Hand-finished and profiled.
Stage 6: Curing (7-14 days)
Essential quiet period. The shell is kept damp for proper curing.
Stage 7: Tiling and Coping (3-5 days)
Waterline tiles, coping stones, feature tiles.
Stage 8: Interior Finish (2-3 days)
Pebblecrete, glass-bead, or full tiling applied.
Stage 9: Equipment and Fencing (3-5 days)
Pump, filter, chlorinator, heater, lights, automation, fence.
Stage 10: Fill and Handover (1-2 days)
Pool filled, equipment commissioned, water balanced, handover walkthrough.
Total Timeline
Design + approvals: 3-6 weeks. Construction: 6-10 weeks. Total: 9-16 weeks.